Typical applications/TA-34Reference

Lane Closure with a Temporary Traffic Barrier

Lane closure protected by temporary concrete barrier.

MUTCD Figure 6P-34

Posted speed limit, off-peak 85th-percentile speed prior to work starting, or anticipated operating speed.

ft

How far traffic is moved sideways — usually the width of the closed lane.

This typical application does not have a generator yet, so it cannot be opened in the builder. The computed geometry below still applies.

Computed for your conditions

MUTCD 11th Ed

merging taper

at least L

245 ft

Base L

Table 6B-4

245 ft

Device spacing in taper

1 × speed, Section 6K.01

35 ft

Device spacing on tangent

2 × speed, Section 6K.01

70 ft

Advance warning area

Table 6B-1

300 ft

Longitudinal buffer

Table 6B-2

250 ft

Total zone length

1095 ft